originally posted on remsauce.blogspot.com
The project took place in Pulau Indah for chemical plant expansion. The duration for the completion is around one year, starting with the piling and closed with a final inspection from BOMBA and the client. I only focused most on mechanical works above than other works.
So here it is.
Sorry I have to skip the civil works for tank foundation, since I don't have the pictures; it is all kept in the memory card which I sent to the main office. I told them to post it, but they didn't.
The civil works for tank foundation was mostly piling, and then followed with reinforcement bar, and finally the concreting. So, from here, let's move to the first picture.
Laying Bitumen to the tank foundation |
Laying Bitumen to the tank foundation |
Laying Bottom Plate |
Shell Manhole opening |
Shell Manhole opening |
Pipe rack footing construction |
Pipe rack footing construction - concreting |
Shell plate installation in progress |
Far view of works on site |
Installation of pre-fabricated pipe support |
Tank roof truss stacked together |
Laying off 4" piping to the pipe support |
General progress |
Construction of pump shed footing |
Pre-fabricated shell manhole |
Construction of pump shed in progress |
General works in progress |
Hacking pavement for future underground electrical cable installation |
Hacking pavement for installation of underground electrical cables. |
Existing piping and cables underground |
Bad weather should be recorded because it is intefering the work progress. |
Pipe supports installed |
Reinforcement plate ready for the shell manhole. |
Site General View |
Shell plate welding in progress for vertical and horizontal seams. |
Tank storage |
Concreting work in progress |
Pump Shed floor slab concreting in progress. |
Installation of roof truss in progress. |
Excavation works for pipe footing installatin between tanks. |
Installation of roof truss in progress. |
Pre-fabrication of intertank walkway. |
More progress for pump shed footing and plinth. |
General view of the roof truss |
General view of the roof truss. |
Installation on spiral stairs. |
Installation of gate valves at tank nozzles. |
Installation of gate valves for tank nozzles. |
General View. |
General view of piping at the exchange hose area. |
Installed spiral stairs. |
Different view at the exchange hose area. |
remcauce, amik apa? chemical ker?
ReplyDeletesaya ni budak mekanikal engineering, universiti malaysia pahang. sekarang da ikut fabrication.
ReplyDelete